Our strength in estimating and pre-project planning allows us to provide our clients with certainty in price, schedule, and performance. We’ve supported our clients to meet the changing power consumption trends and generating strategies by constructing cogeneration, combined-cycle, geothermal and waste-to-energy generation and resource facilities.
We are experience in a variety of contracting methods from EPC contractor to the general contractor. Unlike many of our competitors, we self-perform most major craft disciplines, providing time, cost and scheduling efficiencies, as well as in-house expertise and seamless performance for our clients.
Facility retrofits often present unique challenges, especially when existing structures and original drawings do not match. Kiewit used laser scanning technology to develop a 3-D model of the existing Southwest Power Station, allowing the project team to identify problems before they could affect the project schedule or budget.
In a joint venture,TIC with Kiewit Power Engineers, was the EPC contractor for a 620 MW 2x1 combined cycle gas fired power plant.
In this $480 million project, TIC and MHI are completing engineering, procurement, site work, civil work, piping, electrical and instrumentation, turnover, and completion scopes. Major installed equipment includes a 380 ft. tall CO2 absorber tower, a CO2 compressor, a 120 ft. tall flue gas quencher, regenerator, and the CO2 stripper tower.
Along the Ohio River just south of where Indiana, Ohio and Kentucky meet, sits the Ghent Generating Station — one of the most environmentally sound and technologically advanced coal-fired generating plants in the nation.
TIC-The Industrial Company was the EPC contractor for the design, procurement, construction and startup of the 24 megawatt Steamboat geothermal project.
Industrial Company was the EPC contractor for a 165 megawatt single-flash geothermal power plant in Leyte, Philippines.
TIC-The Industrial Company was the managing partner in a joint venture for the construction of this 118 megawatt power plant in the Upper Mahiao region of Leyte Island in the Philippines.
TIC-The Industrial Company was the EPC contractor for the design, procurement, construction and startup of this 22.6 megawatt geothermal project.
TIC-The Industrial Company was the general contractor for a 43.5 megawatt hydroelectric power plant and new intake structure with penstock on the Snake River.
TIC-The Industrial Company teamed with Power Engineers to design and build the Aragonne Mesa wind generation farm located southwest of Santa Rosa, New Mexico.
10055 Trainstation Circle
Lone Tree, Colorado 80124
720-920-4200
833-281-5273